CX-011830: Categorical Exclusion Determination

Malin Substation Storm Drain and Switchyard Rock Improvements CX(s) Applied: B1.3 Date: 02/06/2014 Location(s): Oregon Offices(s): Bonneville Power Administration

Office of NEPA Policy and Compliance

February 6, 2014
Estimated Read Time   min
Malin Substation Storm Drain and Switchyard Rock Improvements
CX(s) Applied: B1.3
Date: 02/06/2014
Location(s): Oregon
Offices(s): Bonneville Power Administration

Bonneville Power Administration (BPA) proposes to improve the drainage system and replace the crushed rock in the Malin Substation switchyard. Existing yard rock and drainage systems are not performing their functions which have resulted in unsafe working conditions.