Bryan Mound Substation Upgrade to 138 Kilovolts CX(s) Applied: B1.3 Date: 12/17/2013 Location(s): Texas Offices(s): Strategic Petroleum Reserve Field Office
Office of NEPA Policy and Compliance
December 17, 2013Bryan Mound Substation Upgrade to 138 Kilovolts
CX(s) Applied: B1.3
Date: 12/17/2013
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office
Subcontractor shall provide all labor, tools, equipment, materials, services, transportation, storage, and supervision required to upgrade the Bryan Mound substation to 138 kilovolts.
CX(s) Applied: B1.3
Date: 12/17/2013
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office
Subcontractor shall provide all labor, tools, equipment, materials, services, transportation, storage, and supervision required to upgrade the Bryan Mound substation to 138 kilovolts.