Parker Substation 161 Kilovolt 2013 Breaker Replacement CX(s) Applied: B4.6 Date: 05/17/2013 Location(s): California Offices(s): Western Area Power Administration-Desert Southwest Region
Office of NEPA Policy and Compliance
May 17, 2013Parker Substation 161 Kilovolt 2013 Breaker Replacement
CX(s) Applied: B4.6
Date: 05/17/2013
Location(s): California
Offices(s): Western Area Power Administration-Desert Southwest Region
Western Area Power Administration (Western) proposes to replace 5 existing 161 kilovolt (kV) oil power circuit breakers with SF6 gas power circuit breakers in the Parker 161-kV Substation.
CX(s) Applied: B4.6
Date: 05/17/2013
Location(s): California
Offices(s): Western Area Power Administration-Desert Southwest Region
Western Area Power Administration (Western) proposes to replace 5 existing 161 kilovolt (kV) oil power circuit breakers with SF6 gas power circuit breakers in the Parker 161-kV Substation.