CX-010137: Categorical Exclusion Determination

Correct Obstruction in the Sprinkler System on Level 3 of HB-Line CX(s) Applied: B2.5 Date: 03/11/2013 Location(s): South Carolina Offices(s): Savannah River Operations Office

Office of NEPA Policy and Compliance

March 11, 2013
Estimated Read Time   min
Correct Obstruction in the Sprinkler System on Level 3 of HB-Line
CX(s) Applied: B2.5
Date: 03/11/2013
Location(s): South Carolina
Offices(s): Savannah River Operations Office

Modify the sprinkler system on Level 3 of HB-Line to provide adequate floor area coverage. The areas impacted by the change are Rooms 311A and 304.