CX-008882: Categorical Exclusion Determination

Sno-King Substation Expansion CX(s) Applied: B4.11 Date: 08/08/2012 Location(s): Washington Offices(s): Bonneville Power Administration

Office of NEPA Policy and Compliance

August 8, 2012
Estimated Read Time   min
Sno-King Substation Expansion
CX(s) Applied: B4.11
Date: 08/08/2012
Location(s): Washington
Offices(s): Bonneville Power Administration

Bonneville Power Administration (BPA) is proposing to expand its Sno-King Substation’s fenced electrical yard by approximately 0.2 acres to accommodate new equipment.