CX-036448: FY22-FY24 The Dalles, Bundle No. 2 Priority Poles Replacement Project

Bonneville Power Administration (BPA) proposes to replace in-kind wood pole structures and associated structural/electrical components (e.g., cross…

Office of NEPA Policy and Compliance

September 3, 2026
Estimated Read Time   min

Bonneville Power Administration (BPA) proposes to replace in-kind wood pole structures and associated structural/electrical components (e.g., cross arms, insulators, guy anchors, etc.) along the Big Eddy-Demoss and Demoss-Fossil transmission lines. Additionally, the project includes road maintenance and reconstruction of access roads to access the structures on the Big Eddy-Demoss and Demoss-Fossil and additionally on the Hood River-The Dalles transmission line, which is located in the general area. All project locations are in The Dalles transmission line maintenance (TLM) District.