The Bureau of Land Management (BLM) prepared an environmental assessment (EA) for the McMullen Valley Transmission Line Project (DOE/EA-2292). The BLM is the lead federal agency in the National Environmental Policy Act (NEPA) process and WAPA and BOR are cooperating agencies.
Office of NEPA Policy and Compliance
November 6, 2026McMullen Valley Transmission Line Project; La Paz County, Arizona
The Bureau of Land Management (BLM) prepared a final environmental assessment (EA) for the McMullen Valley Transmission Line Project (DOE/EA-2292), which assesses the potential environmental impacts associated with the BLM’s potential approval of EAGL’s right-of-way (ROW) application, Western Area Power Administration's (WAPA) potential approval of the requested interconnection, and the Bureau of Reclamation's (BOR) potential approval of modifications to BOR-owned facilities at the Harcuvar Substation.
Note that WAPA, as the agency responsible for the interconnection decision, and the BOR, as the agency responsible for the Harcuvar Substation, served as cooperating agencies to the EA.
View complete Environmental Assessment.
For more information, see DOE/EA-2292: McMullen Valley Transmission Line Project; La Paz County, Arizona.