Rebuild of approximately 6.56 miles of existing 69 kV transmission line within existing utility right-of-way between the White Pine and Lowland sub…
Office of NEPA Policy and Compliance
July 16, 2026Rebuild of approximately 6.56 miles of existing 69 kV transmission line within existing utility right-of-way between the White Pine and Lowland substations, including structure replacement (approximately 75 wooden poles), reconductoring, grounding improvements, static wire installation, right-of-way trimming and restoration of disturbed areas.