The project team will (1) acquire and qualify magnesium-manganese oxide material
Office of NEPA Policy and Compliance
August 5, 2021The project team will (1) acquire and qualify magnesium-manganese oxide material; (2) test and validate 10 kWh and 100kWh thermochemical modules; (3) develop comprehensive design for thermal energy storage unit; and (4) complete site preparation, installation, and plant operation for prototype gas turbine generator, thermal storage module and integrated system.