CX-019753: Remove Presumed Asbestos Containing Material Gaskets from Pump 004 in Maintenance Shop

The gaskets between the flanges on the #4 river water pump have to be removed. This will allow construction to bead blast the river water pump. The…

Office of NEPA Policy and Compliance

February 28, 2019
Estimated Read Time   min

The gaskets between the flanges on the #4 river water pump have to be removed. This will allow construction to bead blast the river water pump. The asbestos competent person will be the individual performing the removal at the 704-C maintenance shop. Bead plasting activities will occur at the 725-2N Blast Building and are covered under Environmental Evaluation Checklist # PBU-N-2014-0003, Rev. 1.