CX-007994: Categorical Exclusion Determination

Upgrade of the Existing Septic System at the Redmond Substation and Maintenance Facility CX(s) Applied: B4.6 Date: 02/08/2012 Location(s): Oregon Offices(s): Bonneville Power Administration

Office of NEPA Policy and Compliance

February 8, 2012
Estimated Read Time   min
Upgrade of the Existing Septic System at the Redmond Substation and Maintenance Facility
CX(s) Applied: B4.6
Date: 02/08/2012
Location(s): Oregon
Offices(s): Bonneville Power Administration

The project involves replacing the existing septic drain field adjacent to the maintenance building within the Redmond Substation and Maintenance Facility.