Record of Categorical Exclusion for Driver Inspection of Bryan Mound 36 inch Raw Water Pipeline CX(s) Applied: B1.3 Date: 12/20/2011 Location(s): Texas Offices(s): Strategic Petroleum Reserve Field Office
Office of NEPA Policy and Compliance
December 20, 2011Record of Categorical Exclusion for Driver Inspection of Bryan Mound 36 inch Raw Water Pipeline
CX(s) Applied: B1.3
Date: 12/20/2011
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office
Subcontractor shall provide all supervision, labor, materials, tools, supplies, transportation, facilities, equipment, and services required to perform piping inspection, ultrasonic inspections, and take epoxy impressions and photographs of the Bryan Mound Raw Water pipeline from the pig receiver to the High Pressure Pump Pad pig launcher.