American Recovery and Reinvestment Act: Pilot Testing of a Membrane System for Post-Combustion Carbon Dioxide (CO2) CaptureCX(s) Applied: A1, A9, A11, B3.6Date: 10/01/2010Location(s): Holbrook, ArizonaOffice(s): Fossil Energy, National Energy Technolog...
Office of NEPA Policy and Compliance
October 1, 2010CX(s) Applied: A1, A9, A11, B3.6
Date: 10/01/2010
Location(s): Holbrook, Arizona
Office(s): Fossil Energy, National Energy Technology Laboratory
Install and operate a 1 megawatt (20 ton of carbon dioxide per day) membrane carbon dioxide (CO2) capture system (skid mounted - 500 square foot footprint) at the Arizona Public Service's (APS) Cholla Power Plant. Continued testing of 1 ton per day (TPD) CO2 membrane unit at APS.