May 5, 2011Glen Canyon substation Transformer Addition
CX(s) Applied: B4.6
Date: 05/05/2011
Location(s): Coconino County, Arizona
Office(s): Western Area Power Administration-Desert Southwest Region
Western proposes add a second 230/138 kilovolt (kV) autotransformer at Glen Canyon Substation to provide redundant power to Garkane Energy. A used 230/138 transformer from Hayden Substation will be transported to Glen Canyon for installation. A new foundation will be installed within the existing fenced and graveled substation area. New 230-kV and 138-kV bus work will also be installed. The new configuration includes the addition of two new 138-kV circuit breakers. A temporary transmission line connection, called a shoofly, will be constructed; it will consist of wood pole structures.
CX(s) Applied: B4.6
Date: 05/05/2011
Location(s): Coconino County, Arizona
Office(s): Western Area Power Administration-Desert Southwest Region
Western proposes add a second 230/138 kilovolt (kV) autotransformer at Glen Canyon Substation to provide redundant power to Garkane Energy. A used 230/138 transformer from Hayden Substation will be transported to Glen Canyon for installation. A new foundation will be installed within the existing fenced and graveled substation area. New 230-kV and 138-kV bus work will also be installed. The new configuration includes the addition of two new 138-kV circuit breakers. A temporary transmission line connection, called a shoofly, will be constructed; it will consist of wood pole structures.