CX-005140: Categorical Exclusion Determination

G0313 Coyote Crest Wind Park Interconnection RequestCX(s) Applied: B1.7, B4.6Date: 02/09/2011Location(s): Lewis County, WashingtonOffice(s): Bonneville Power Administration

Office of NEPA Policy and Compliance

February 9, 2011
Estimated Read Time   min
G0313 Coyote Crest Wind Park Interconnection Request
CX(s) Applied: B1.7, B4.6
Date: 02/09/2011
Location(s): Lewis County, Washington
Office(s): Bonneville Power Administration

In response to EverPower?s interconnection request, Bonneville Power Administration (BPA) is planning to integrate EverPower?s 120-megawatt Coyote Crest Wind Park project into its balancing authority (BA). The proposed point of interconnect is at Grays Harbor Public Utility District's (PUD?s) South Elma Substation. In order to integrate the proposed generation, BPA transmission services would install, own, and operate metering, telemetry, and Remedial Action Scheme equipment within EverPower's Coyote Crest Substation, Grays Harbor PUD's South Elma Substation, BPA's Satsop, Olympia, Chehalis, and Longview Substations as well as in BPA's Dittmer and Munro Control Centers.

DOCUMENT(S) AVAILABLE FOR DOWNLOAD