Fiscal Year 2011 Pasco District Wood Pole Replacement ProjectsCX(s) Applied: B1.3Date: 04/11/2011Location(s): Pasco District, WashingtonOffice(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
April 11, 2011CX(s) Applied: B1.3
Date: 04/11/2011
Location(s): Pasco District, Washington
Office(s): Bonneville Power Administration
Bonneville Power Administration proposes to replace deteriorating wood poles and associated structural/electrical components (e.g. cross arms, insulators, guy anchors, etc.) along the subject transmission line. Replacement will be in-kind and will utilize the existing holes to minimize ground disturbance. If necessary, an auger will be used to remove any loose soil from the existing hole prior to new wood pole placement. New landing construction is not planned or anticipated at these locations.