CX-017183: City of Vancouver Water Line Installation

Categorical Exclusion Determination

Office of NEPA Policy and Compliance

October 23, 2017
Estimated Read Time   min

Bonneville Power Administration (BPA) is proposing to allow the City of Vancouver to install a water line within BPA transmission line right-of-way (ROW). The 8-inch PVC water line would be buried at a depth of 3 feet near structure 34/3 on the North Bonneville-Ross No. 2 transmission line. The water line would be buried adjacent to an existing sewer main for approximately 200 feet and then connect into an existing manhole.