CX-001664: Categorical Exclusion Determination

Provide Breathing Air Package Units for Building 221-F Warm Crane Maintenance Area and TruckwellCX(s) Applied: B2.5Date: 02/12/2010Location(s): Aiken, South CarolinaOffice(s): Environmental Management, Savannah River Operations Office

Office of NEPA Policy and Compliance

February 12, 2010
Estimated Read Time   min

Provide Breathing Air Package Units for Building 221-F Warm Crane Maintenance Area and Truckwell
CX(s) Applied: B2.5
Date: 02/12/2010
Location(s): Aiken, South Carolina
Office(s): Environmental Management, Savannah River Operations Office


Design, procure and install two, permanent, skid-mounted, electric-driven, air-cooled, breathing air (BA) units to replace four, existing, portable, diesel-driven, BA units for providing BA to building 221-F warm crane maintenance area (WCMA) and truckwell to support transuranic waste remediation project work activities.

DOCUMENT(S) AVAILABLE FOR DOWNLOAD