CX-005676: Categorical Exclusion Determination

Murray-Custer #1 Transmission Line Wood Pole ReplacementCX(s) Applied: B1.3Date: 04/15/2011Location(s): Snohomish County, WashingtonOffice(s): Bonneville Power Administration

Office of NEPA Policy and Compliance

April 15, 2011
Estimated Read Time   min
Murray-Custer #1 Transmission Line Wood Pole Replacement
CX(s) Applied: B1.3
Date: 04/15/2011
Location(s): Snohomish County, Washington
Office(s): Bonneville Power Administration

Bonneville Power Administration (BPA) proposes to replace deteriorating wood poles and associated structural/electrical components (e.g. crossarms, insulators, guy anchors) along the subject transmission lines. Pole replacement will be in-kind and will utilize the existing holes to minimize ground disturbance. If necessary, an auger will be used to remove any loose soil from the existing hole prior to new wood pole replacement. Landing construction is not planned or anticipated at these locations.

DOCUMENT(S) AVAILABLE FOR DOWNLOAD