Categorical Exclusion Determination
Office of NEPA Policy and Compliance
November 30, 2015The proposed scope of work includes removing several machining centers using various disposition paths including relocation in the machine shop, trade-in for purchase of new machines, and excess. Minor demolition would be conducted to remove abandoned conduit and support structures associated with the existing machining centers. Construction and reinforcement of the floor would be needed to support the new machining center(s). Installation of future machining center(s) (machines other than the Mazak VTC-800) is also included in this work scope along with other facility modifications to accommodate the machines.