CX-015712: Categorical Exclusion Determination

KAC Disassembly Transfer Bay Floor Upgrade CX(s) Applied: B1.15, B2.1Date: 07/26/2016 Location(s): South CarolinaOffices(s): Savannah River Operations Office

Office of NEPA Policy and Compliance

July 26, 2016
Estimated Read Time   min

KAC Disassembly Transfer Bay Floor Upgrade
CX(s) Applied: B1.15, B2.1
Date: 07/26/2016
Location(s): South Carolina
Offices(s): Savannah River Operations Office

Install a concrete slab on existing 6-inch slab on grade in the KAC Transfer Bay area. The top slab is approximately 4 inches thick and is approximately 40 feet X 63 feet. A concrete curb will be installed to prevent outside rain water from entering this area.