CX-015338: Categorical Exclusion Determination

Wireless Test Bed Main Gate Shelter Complex Non-Emergency Generator Installation CX(s) Applied: B1.31Date: 42548 Location(s): IdahoOffices(s): Nuclear Energy

Office of NEPA Policy and Compliance

June 27, 2016
Estimated Read Time   min

Wireless Test Bed Main Gate Shelter Complex Non-Emergency Generator Installation
CX(s) Applied: B1.31
Date: 42548
Location(s): Idaho
Offices(s): Nuclear Energy

The proposed action would provide the Wireless Test Bed program (WTB) with the ability to maintain electrical power to B27-Maingate Shelters #1, #2, and #3 during planned and unplanned power outages. This action includes removal of electrical equipment, installation of an outdoor Tier 4 non-emergency generator and concrete slab, sidewalk demolition and repair, and installation of alternating transfer switch, disconnects, duct banks, conduit, and wire sufficient for maintaining shelter operations.

Document(s) Available for Download