The window in the Production Control Center (PCC) at the Advanced Test Reactor (ATR), building TRA-670, is not operational and a new, functional window is needed. The proposed action would construct a new window to the PCC. The activity would require block removal for installation of a framed opening on the south wall. The new opening would be approximately 39 in. X 32 in. and constructed on a non-load bearing wall. The opening would be framed with finished wood and finished. Glass would not be installed in the new opening.