Mingo Ditch Structure Replacement Project, Line 3007, Structures 930-932 (Part B4.6) CX(s) Applied: B4.6Date: 03/11/2016 Location(s): MissouriOffices(s): Southwestern Power Administration
Office of NEPA Policy and Compliance
March 11, 2016Mingo Ditch Structure Replacement Project, Line 3007, Structures 930-932 (Part B4.6)
CX(s) Applied: B4.6
Date: 03/11/2016
Location(s): Missouri
Offices(s): Southwestern Power Administration
Southwestern Power Administration is modifying three transmission line structures in order to maximize the proper aerial spanning of electrical lines across the Mingo Ditch.