Damper Installations on the Cougar-Thurston #1 Transmission Line Corridor CX(s) Applied: B1.3Date: 02/05/2016 Location(s): OregonOffices(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
February 5, 2016Damper Installations on the Cougar-Thurston #1 Transmission Line Corridor
CX(s) Applied: B1.3
Date: 02/05/2016
Location(s): Oregon
Offices(s): Bonneville Power Administration
Bonneville Power Administration (BPA) proposes to perform installation of 666 dampers, 32 spiral dampers, and in-kind replacement of 10 wood pole structures along the Cougar-Thurston #1 transmission line corridor.