CX-014990: Categorical Exclusion Determination

Longview-Allston No. 1-2, Structure 2/2 Slope Inclinometer Installation CX(s) Applied: B3.1Date: 05/05/2016 Location(s): WashingtonOffices(s): Bonneville Power Administration

Office of NEPA Policy and Compliance

May 5, 2016
Estimated Read Time   min

Longview-Allston No. 1-2, Structure 2/2 Slope Inclinometer Installation
CX(s) Applied: B3.1
Date: 05/05/2016
Location(s): Washington
Offices(s): Bonneville Power Administration

Bonneville Power Administration (BPA) proposes to bore three holes for installation of slope inclinometers around Structure 2/2 on the Longview-Allston No. 1-2 Transmission Line, and to construct approximately 416 feet of new road to access the proposed boring locations.