Verizon Longacre Wireless Installation CX(s) Applied: B1.19Date: 05/17/2016 Location(s): OregonOffices(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
May 17, 2016Verizon Longacre Wireless Installation
CX(s) Applied: B1.19
Date: 05/17/2016
Location(s): Oregon
Offices(s): Bonneville Power Administration
Bonneville Power Administration (BPA) proposes to allow Verizon Wireless to install an unmanned telecommunications facility at base tower 17/1 of the Pearl-Keeler Line #1 transmission line.