NERC Alert Phase III Transmission Line Structure Replacement Project CX(s) Applied: B4.6Date: 04/16/2015 Location(s): OklahomaOffices(s): Southwestern Power Administration
Office of NEPA Policy and Compliance
April 16, 2015NERC Alert Phase III Transmission Line Structure Replacement Project
CX(s) Applied: B4.6
Date: 04/16/2015
Location(s): Oklahoma
Offices(s): Southwestern Power Administration
Southwestern Power Administration proposes to replace approximately 300 structures located in several counties throughout Oklahoma, Arkansas, and Missouri, where, at elevated temperatures, the distance between the conductor and the ground could violate the requirements of the National Electrical Safety Code. To remediate these potential concerns, and to ensure the safety of the public and the continuity of the transmission line infrastructure, Southwestern Power Administration will replace these structures with taller structures and add or modify these structures.