Horn Rapids Tap Disconnect Additions CX(s) Applied: B4.6Date: 06/17/2015 Location(s): WashingtonOffices(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
June 17, 2015Horn Rapids Tap Disconnect Additions
CX(s) Applied: B4.6
Date: 06/17/2015
Location(s): Washington
Offices(s): Bonneville Power Administration
Bonneville Power Administration (BPA) proposes to replace and/or install new switching structures at the two project locations. At Quilcene Substation, two replacement wood pole structures and the new switches will be installed near the original location in a realigned configuration.
CX(s) Applied: B4.6
Date: 06/17/2015
Location(s): Washington
Offices(s): Bonneville Power Administration