Record of Categorical Exclusion Determination to Replace Piping Header at Bryan Mound RWIS and RWIP (BM-MM-1027) CX(s) Applied: B1.3Date: 02/18/2015 Location(s): TexasOffices(s): Strategic Petroleum Reserve Field Office
Office of NEPA Policy and Compliance
February 18, 2015Record of Categorical Exclusion Determination to Replace Piping Header at Bryan Mound RWIS and RWIP (BM-MM-1027)
CX(s) Applied: B1.3
Date: 02/18/2015
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office
Subcontractor shall provide all labor, tools, materials, equipment, and supervision required to replace the 24" piping on the discharge of the Bryan Mound (BM) Raw Water Intake Pumps (BMP-276, 277, 278, 279), the connected 36" common discharge header, the 10" recirculation piping at the Raw Water Injection Pump Pad, and to install full encirclement sleeves on various sections of piping on the discharge of the injection pumps.