CX-012656: Categorical Exclusion Determination

North Bend Communication Site Engine Generator Replacement CX(s) Applied: B1.3Date: 41848 Location(s): WashingtonOffices(s): Bonneville Power Administration

Office of NEPA Policy and Compliance

July 28, 2014
Estimated Read Time   min
North Bend Communication Site Engine Generator Replacement
CX(s) Applied: B1.3
Date: 41848
Location(s): Washington
Offices(s): Bonneville Power Administration

Bonneville Power Administration (BPA) proposes to maintain its North Bend communication site by replacing the existing engine generator, the associated controls and ventilation system, the existing propane tanks, and underground propane lines that connect the tank to the engine generator.