The project involves replacement of approximately 16.4 miles of existing 2/0 ACSR and No. 2 ACSR electric distribution lines with upgraded 336 ACSR…
Office of NEPA Policy and Compliance
December 12, 2025The project involves replacement of approximately 16.4 miles of existing 2/0 ACSR and No. 2 ACSR electric distribution lines with upgraded 336 ACSR conductors to improve capacity and reliability. Existing poles and structures will be utilized where feasible. No new right-of-way acquisition or major site excavation is required.