Pole Replacement: The project entails the replacement of 61 existing wooden power distribution poles with steel poles. Conductor Wire Upgrade: Appr…

Office of NEPA Policy and Compliance

July 18, 2025
minute read time

Pole Replacement: The project entails the replacement of 61 existing wooden power distribution poles with steel poles. Conductor Wire Upgrade: Approximately 27,350 linear feet of existing conductor wire will be replaced with 477 AAC (All Aluminum Conductor) and 3/0 ACSR (Aluminum Conductor Steel Reinforced) wire. Smart Meter Installation: Installation of approximately 4,200 new smart meters across all service locations within existing footprint.