CX-032683: Northern PA Rural Grid Resilience Project

Install SCADA infrastructure on an existing substation at 6 locations (Austin, Columbia Cross Roads, Germania, Liberty, Milan, and Nelson). No grou…

Office of NEPA Policy and Compliance

December 4, 2024
minute read time

Install SCADA infrastructure on an existing substation at 6 locations (Austin, Columbia Cross Roads, Germania, Liberty, Milan, and Nelson). No ground disturbance will take place at these locations. Replace 1800 ft of underground cable and replace utility poles at 5 existing substation locations (Ayers Corner, Columbia Crossroads, Germania, Nelson and Westfield).