CX-020775: Paul-Olympia No. 1 Access Road Improvement Project

BPA proposes to perform routine maintenance along the access roads and structure spur roads of the Paul-Olympia No. 1 transmission line, between st…

Office of NEPA Policy and Compliance

October 4, 2019
minute read time

BPA proposes to perform routine maintenance along the access roads and structure spur roads of the Paul-Olympia No. 1 transmission line, between structures 4/1 to 5/3 and 12/4 to 12/5. To maintain access to existing towers and transmission lines, BPA is proposing to add one cross-drain culvert; clean two existing culverts; add four ditch reliefs, six drain dips, and five waterbars; perform minor blading, shaping, grading, and adding rock (improvements) to approximately 7,850 feet of existing serviceable access and structure spur roads; reconstruct approximately 275 feet of road; and clear and grub 275 feet of road. General equipment used for this type of project includes mowers, graders, rollers, excavators, and dump trucks.