BPA is proposing to perform routine road maintenance to approximately 2.69 linear miles of existing access road for the Grand Coulee – Chief Joseph…
Office of NEPA Policy and Compliance
June 19, 2019BPA is proposing to perform routine road maintenance to approximately 2.69 linear miles of existing access road for the Grand Coulee – Chief Joseph No. 2 transmission line, between towers 31/8 and 32/4 in Douglas County, WA. Access road work would include replacing 1 culvert, adding 2 waterbars, and performing minor blading, shaping, grading, and adding rock to approximately 10,000 feet of existing serviceable access and structure spur roads. Additionally, BPA would construct new spur roads to structures 31/7 and 32/2; approximately 375 linear feet in length. General equipment used for this type of project includes: graders, rollers, excavators, and dump trucks.