CX-017062: Developing and Testing Radiation Resistant High Density Foam

Categorical Exclusion Determination

Office of NEPA Policy and Compliance

June 27, 2017
minute read time

Environmental evaluation checklist has been revised to cover the installation of a 300,000-gallon fire water tank and electric-driven fire water pump and diesel-driven fire water pump to be installed between old 713-A and 713-1A pads and to designate the domestic water system as a back-up supply to the pumps when the fire tank is unavailable due to painting, etc.  Rev.1 also is needed to cover the geotechnical work.  Existing fire water pumps at 784-A are to be removed prior to 784-A powerhouse demolition (Not a part of this environmental evaluation checklist).  Rev. 2 extends activity end date.