CX-016749: Pilot Test of Novel Electrochemical Membrane System for Carbon Dioxide Capture and Power Generation

Categorical Exclusion Determination

Office of NEPA Policy and Compliance

August 15, 2017
Estimated Read Time   min

Three Megawatt electric (60 carbon dioxide tons per day) electrochemical separations system to be pilot tested at Plant Barry Generating Station. The project involves design, build pilot skids, operate, and decommissioning.