CX-016400: Driscoll-Naselle 21/2 Mile (Powerline Road) Access Road Maintenance Project

Categorical Exclusion Determination

Office of NEPA Policy and Compliance

February 2, 2017
Estimated Read Time   min

Bonneville Power Administration proposes to conduct maintenance activities along powerline road that leads to the Driscoll-Naselle transmission line corridor in the 21/2 mile. Activities include installation of three 18 inch cross drain ditch culverts, one water bar, road surface contouring, and placement of crushed rock road surface.