Categorical Exclusion Determination
Office of NEPA Policy and Compliance
October 25, 2016Subcontractor shall provide all labor, materials, equipment and supervision required to design and construct modifications to replace the existing BM internal floating roof tank
crude oil tank (BMT-2) with an external floating roof tank. Construction cannot stat until an environmental air permit has been obtained by the SPR, CX: Based on the final tank design.
Tank also includes associated civil (drainage, elevated walkway, staircases, sidewalk), electrical (lighting system) and instrumentation (tank level indicators) work.