Replace Section of 36-inch Crude Oil Pipeline at Hillebrandt Bayou
CX(s) Applied: B5.4
Date: 42534
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office

Subcontractor shall furnish all labor, tools, equipment, materials, consumables, services, transportation, storage, and supervision required to replace the corroded segment of 36” Big Hill Crude Oil Pipeline crossing beneath Hillebrandt Bayou within the existing 50’ pipeline right-of-way.