Subcontract Engineering Services for BMT-2 Conversion (BM-MM-740E) CX(s) Applied: B1.3Date: 04/25/2016 Location(s): TexasOffices(s): Strategic Petroleum Reserve Field Office

Office of NEPA Policy and Compliance

April 25, 2016
Estimated Read Time   min

Subcontract Engineering Services for BMT-2 Conversion (BM-MM-740E)
CX(s) Applied: B1.3
Date: 04/25/2016
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office

Subcontractor shall furnish Professional Engineering services to support the Strategic Petroleum Reserve M&O contractor in connection with the construction, testing and inspection for the conversion of crude oil tank BMT-2 from an internal floating roof to an external floating roof under project Bryan Mound (BM) MM-740C. Tasks include providing engineering services for the necessary repairs to the BMT-2 tank floor and construction support services for ongoing field construction for project BM-MM-740C.