Installation of Metering Equipment near North Bench and Bonners Ferry Substations CX(s) Applied: B4.9Date: 04/01/2016 Location(s): IdahoOffices(s): Bonneville Power Administration

Office of NEPA Policy and Compliance

April 1, 2016
Estimated Read Time   min

Installation of Metering Equipment near North Bench and Bonners Ferry Substations
CX(s) Applied: B4.9
Date: 04/01/2016
Location(s): Idaho
Offices(s): Bonneville Power Administration

Bonneville Power Administration (BPA) proposes to allow Northern Lights, Inc. to install metering equipment on concrete pads adjacent to the North Bench and Bonners Ferry substations.