Chimney Hill Solar Project Interconnection with PEC and Interface with the SWPA Tupelo Switchyard CX(s) Applied: A9Date: 03/03/2016 Location(s): OklahomaOffices(s): Southwestern Power Administration
Office of NEPA Policy and Compliance
March 3, 2016Chimney Hill Solar Project Interconnection with PEC and Interface with the SWPA Tupelo Switchyard
CX(s) Applied: A9
Date: 03/03/2016
Location(s): Oklahoma
Offices(s): Southwestern Power Administration
Southwestern Power Administration (SWPA) proposes to interface with Peoples Electric Cooperative (PEC) to accommodate the Chimney Hill Solar Project Interconnection. SWPA will not require adjustments to the existing relay/protection system that already exist, at the interface of the SWPA & PEC systems.