FY15 Wood Pole Replacement - Kalispell District CX(s) Applied: B1.3Date: 04/21/2015 Location(s): MontanaOffices(s): Bonneville Power Administration
Office of NEPA Policy and Compliance
April 21, 2015FY15 Wood Pole Replacement - Kalispell District
CX(s) Applied: B1.3
Date: 04/21/2015
Location(s): Montana
Offices(s): Bonneville Power Administration
Bonneville Power Administration (BPA) proposes to replace a total of twelve deteriorating woo-pole structures and associated structural/electrical components along five different transmission lines in Montana.