Building 12-75B Expansion for UPS and Heating, Ventilation and Air Conditioning Upgrade CX(s) Applied: B1.15, B2.1Date: 03/17/2015 Location(s): TexasOffices(s): Pantex Site Office
Office of NEPA Policy and Compliance
March 17, 2015Building 12-75B Expansion for UPS and Heating, Ventilation and Air Conditioning Upgrade
CX(s) Applied: B1.15, B2.1
Date: 03/17/2015
Location(s): Texas
Offices(s): Pantex Site Office
The project would replace the uninterruptable power supply for 12-75 with an upgraded 200-kilovolt amperes capability. Installation of the higher capacity UPS requires changes to the footprint and electrical/mechanical reconfiguration of building sections. This would include demolition of parts of the hardened structure and rebuilding the electrical and mechanical rooms.