CX-012748: Categorical Exclusion Determination

Big Spring-Sydney 115 Kilovolt Transmission Line Pole Replacement Project, Deuel County, Nebraska CX(s) Applied: B1.3Date: 41845 Location(s): NebraskaOffices(s): Western Area Power Administration-Rocky Mountain Region

Office of NEPA Policy and Compliance

July 25, 2014
Estimated Read Time   min
Big Spring-Sydney 115 Kilovolt Transmission Line Pole Replacement Project, Deuel County, Nebraska
CX(s) Applied: B1.3
Date: 41845
Location(s): Nebraska
Offices(s): Western Area Power Administration-Rocky Mountain Region

Western Area Power Administration (Western) proposes to replace Structures 21 and 37 along the Big Spring to Sidney (BSG-SDT) 115-kV Transmission Line.

Document(s) Available for Download