Curecanti-Lost Canyon 230-Kilovolt Reconductoring Project CX(s) Applied: B1.3 Date: 04/25/2014 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region
Office of NEPA Policy and Compliance
April 25, 2014Curecanti-Lost Canyon 230-Kilovolt Reconductoring Project
CX(s) Applied: B1.3
Date: 04/25/2014
Location(s): Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region
In 2013, Western Area Power Administration (Western) Maintenance crews responded to an emergency involving a downed conductor along the Curecanti-Lost Canyon (CCI-LCN) 230-Kilovolt Transmission Line that had fallen across Colorado Highway 145. Crews immediately repaired the downed conductor between Structures 43/2 and 43/3. Western is proposing to reconductor the remaining phases of the transmission line along the spans between Structures 43/2 to 43/3, 47/4 to 47/3, and 47/3 to 47/2.
CX(s) Applied: B1.3
Date: 04/25/2014
Location(s): Colorado
Offices(s): Western Area Power Administration-Rocky Mountain Region
In 2013, Western Area Power Administration (Western) Maintenance crews responded to an emergency involving a downed conductor along the Curecanti-Lost Canyon (CCI-LCN) 230-Kilovolt Transmission Line that had fallen across Colorado Highway 145. Crews immediately repaired the downed conductor between Structures 43/2 and 43/3. Western is proposing to reconductor the remaining phases of the transmission line along the spans between Structures 43/2 to 43/3, 47/4 to 47/3, and 47/3 to 47/2.