Replace Big Hill Circuit Breakers OCB-4009, 4010 and 4011 CX(s) Applied: B1.33 Date: 06/28/2013 Location(s): Texas Offices(s): Strategic Petroleum Reserve Field Office
Office of NEPA Policy and Compliance
June 28, 2013Replace Big Hill Circuit Breakers OCB-4009, 4010 and 4011
CX(s) Applied: B1.33
Date: 06/28/2013
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office
Subcontractor shall provide all labor, supervision, tools, equipment, and transportation required to furnish three new 138 kilovolt SF6 circuit breakers to replace the existing Big Hill oil circuit breakers OCB-4009, 4010 and 4011.
CX(s) Applied: B1.33
Date: 06/28/2013
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office
Subcontractor shall provide all labor, supervision, tools, equipment, and transportation required to furnish three new 138 kilovolt SF6 circuit breakers to replace the existing Big Hill oil circuit breakers OCB-4009, 4010 and 4011.