CX-010711: Categorical Exclusion Determination

Bryan Mound Brine Disposal Pump Replacement CX(s) Applied: B5.2 Date: 07/03/2013 Location(s): Texas Offices(s): Strategic Petroleum Reserve Field Office

Office of NEPA Policy and Compliance

July 3, 2013
Estimated Read Time   min
Bryan Mound Brine Disposal Pump Replacement
CX(s) Applied: B5.2
Date: 07/03/2013
Location(s): Texas
Offices(s): Strategic Petroleum Reserve Field Office

Subcontractor shall provide all labor, materials, tools, equipment, supervision, and transportation required to supply two pumps to replace the existing Bryan Mound brine disposal pumps, BMP-115 and BMP-116.